A cloud migration finished on schedule with no release freeze for a German fintech

Two DevOps engineers took over the migration mid-flight after the lead left.

Product
Lending platform
Technologies
Kubernetes, Terraform, Azure, GitLab CI
Timeframe
2025 – 2026

The migration had a deadline, a regulator and no owner — we supplied the owner.

The challenge

Their infrastructure lead resigned four weeks into a twelve-week migration. Half the services were containerised, the pipelines were half-rewritten and the audit date did not move.

DE

Freezing releases was not an option: two product commitments were already announced to customers.

The audit date was fixed by the regulator, two product commitments were already public, and half the services were containerised — so the work could neither pause nor restart from scratch.

OPS

In a nutshell, when the company came to us it was grappling with:

  • Infrastructure lead gone four weeks in.
  • Pipelines half rewritten.
  • A fixed regulatory audit date.
  • Two release commitments already announced.

Key solutions

Taking over a cloud migration mid-flight

Holol Alghad

Two of our DevOps engineers picked the work up where it stood, finished the containerisation, rebuilt the pipelines with environment parity, and documented every step for the audit.

Releases continued through the whole migration on a blue-green setup the client's team now runs themselves.

Solutions we provided:

  • Continuity first

    We picked the work up where it stood instead of restarting, so no announced release date moved.

  • Environment parity

    Pipelines rebuilt so staging and production behave the same — the source of most of the pre-migration surprises.

  • Audit-ready documentation

    Every step recorded as the regulator expects, handed over with the runbooks the client's team now uses.

Team on the project

Two engineers who owned the migration

Team built from scratch2DevOps, platform engineering2025 – 2026
With us
  • DevOps
  • Platform engineering

Two DevOps engineers took over a migration already in flight, finished the containerisation, rebuilt the pipelines and documented everything the audit required.

The client's head of technology set priorities; our engineers ran the migration board and the audit evidence pack.

Fully remote, with one on-site week in Frankfurt for the cut-over weekend.

The migration was run remotely, with on-site presence where it counted:

  • Cut-over weekend in Frankfurt
  • Audit preparation sessionswith the client's compliance officer
  • Weekly migration board
  • Handover of runbooksto the client's platform team
  • GermanyDE
  • Saudi ArabiaSA
  • PolandPL
Riyadh

The pipelines and runbooks now belong to the client's own team, who have run two further cut-overs without us.

Within days we had someone who owned the migration again. Nothing was announced late.
DEClient's head of technology

Results

12 weeks
migration completed on time
0
release freezes
-35%
infrastructure cost
100%
audit evidence delivered
Within days we had someone who owned the migration again. Nothing was announced late.
Head of TechnologyLending platform, Germany

Project completed:

A migration that stayed on schedule

Holol Alghad

The client went from a migration with no owner and a fixed audit date to a completed cloud move, rebuilt pipelines and an audit evidence pack — without freezing a single release.

Infrastructure cost fell 35%, the audit passed on the original date, and the client's platform team has since run two further cut-overs on their own.

Holol Alghad

Two DevOps engineers took over mid-flight, finished the containerisation, rebuilt the pipelines with environment parity and documented every step for the regulator.

Taking over someone else's half-finished migration is the hardest thing we do. Finishing it on the original date is the part I am proud of.
FOFaisal Al-OtaibiAccount manager at Holol Alghad